Secured Advance

An advance payment made to the contractor on the basis of the security of materials brought by the contractor to the site of work under constructions called as Secured Advance.

The amount of secured advance should not be more than 75% of the cost of materials brought by the contractor to the site.
For Lime, surkhi, sand, kankar, etc are considered as perishable materials hence no advance is permissible for these materials.
Detailed amount of advance is kept in form 26-A and is attached to R/A bill.